Claiming liquidated damages under the JCT Design and Build Contract 2024
The notices an employer needs to claim liquidated damages under JCT DB 2024, in order: the Non-Completion Notice, the clause 2.29 notices and the Pay Less Notice, with the clauses behind each.
Under the JCT Design and Build Contract 2024, an employer’s right to liquidated damages for late completion depends on notices given in the right order and on time. Miss one and a deduction can be reversed in adjudication, even where the delay itself is not in doubt. This guide sets out each step and the clauses behind it.
In short
- Three notices: a Non-Completion Notice (clause 2.28), a notice that the employer may require or deduct liquidated damages (clause 2.29.1), and a notice requiring payment or stating that it will withhold or deduct them (clause 2.29.2).
- Pay Less Notice: to deduct from a payment, the employer also needs a valid Pay Less Notice (clause 4.10).
- Extensions of time: fixing a later Completion Date cancels the Non-Completion Notice, and liquidated damages for the extended period must be repaid (clauses 2.28 and 2.29.3).
- Termination: new clause 2.29.5 stops liquidated damages at the date the contractor’s employment is terminated.
Start with the Contract Particulars
Liquidated damages are recoverable only at the rate stated in the Contract Particulars for clause 2.29.2, for the Works or for each Section. Check the rate, the period it applies to (usually per week or part of a week) and the Date for Completion. Care is needed with the entry: in Temloc v Errill Properties (1987), the Court of Appeal held that an entry of “£nil” meant the employer could recover nothing for delay, not that it could claim general damages instead.
Step 1: confirm the Completion Date
Liquidated damages run from the Completion Date, which is the Date for Completion as adjusted by any extension of time. The contractor must notify delay and give particulars (clause 2.24), and the employer must decide whether to fix a later Completion Date (clause 2.25). The 2024 edition shortened the employer’s period for deciding from 12 weeks to 8. The employer can also review the Completion Date after practical completion (clause 2.25).
Before claiming, make sure every extension of time application has been decided and the Completion Date is correctly calculated. Deducting from the wrong date invites a challenge, and an undecided application leaves the deduction exposed.
Step 2: the Non-Completion Notice (clause 2.28)
If the contractor fails to complete the Works or a Section by the relevant Completion Date, the employer must issue a Non-Completion Notice (clause 2.28). It should identify the Works or Section and the Completion Date missed, and should be issued promptly once that date passes.
The notice does not survive a later extension. If a new Completion Date is fixed after it has been issued, that cancels the notice, and the employer must issue a further Non-Completion Notice if the contractor then misses the new date (clause 2.28).
Step 3: notice that liquidated damages may be required (clause 2.29.1)
The employer’s right to liquidated damages depends on two conditions: it has issued a Non-Completion Notice, and before the due date for the final payment it has notified the contractor that it may require payment of, or may withhold or deduct, liquidated damages (clause 2.29.1). This second notice is often given with the Non-Completion Notice. Unlike the Non-Completion Notice, it generally remains effective after a later Completion Date is fixed unless the employer withdraws it (clause 2.29.4).
Step 4: requiring payment or deducting (clause 2.29.2)
Once both conditions are met, the employer may, no later than five days before the final date for payment of the final payment, give notice that it either (clause 2.29.2):
- Requires payment: requires the contractor to pay liquidated damages at the rate in the Contract Particulars, or a lower rate stated in the notice, for the period between the Completion Date and practical completion; or
- Will deduct: will withhold or deduct liquidated damages on the same basis.
The notice should state which option applies, the rate and the period, so that the contractor can see how the amount is calculated.
Step 5: the Pay Less Notice (clause 4.10)
To deduct liquidated damages from an interim or final payment, the employer must also give a Pay Less Notice, no later than five days before the final date for payment, stating the sum it considers due and the basis on which it is calculated (clause 4.10). This reflects section 111 of the Housing Grants, Construction and Regeneration Act 1996. Without a valid Pay Less Notice, the employer must pay the notified sum in full and recover the liquidated damages later. A clause 2.29.2 notice may also work as a Pay Less Notice if its content and timing comply, but a separate notice for each payment is safer.
Later extensions, partial possession and termination
- Repayment: if a later Completion Date is fixed after liquidated damages have been recovered, the employer must repay the amounts recovered for the period up to the new date (clause 2.29.3). In Reinwood v L Brown & Sons [2008] UKHL 12, the House of Lords held that a deduction properly made under a valid notice is not invalidated by a later extension; the employer must simply repay the excess.
- Partial possession: where the employer takes possession of part of the Works, the rate of liquidated damages is reduced for the part taken over (clause 2.34).
- Termination: if the contractor’s employment is terminated before practical completion, liquidated damages run only from the Completion Date to the date of termination. After that, the employer cannot require or deduct them, but keeps its other rights, including a claim for general damages (clause 2.29.5). The clause is new in the 2024 edition and reflects the Supreme Court’s decision in Triple Point Technology v PTT [2021] UKSC 29.
Giving the notices
The 2024 edition allows most notices to be given by email to the address in the Contract Particulars, but notices about default and termination may be sent by email only if the parties have opted in (clause 1.7). Notices should be in writing, given by the employer or by the Employer’s Agent on its behalf, and sent to the right address by a permitted method.
What this means in practice
Liquidated damages are not automatic. They are a contractual entitlement that depends on a sequence of notices, and adjudicators apply that sequence strictly. The most common failures are not issuing a Non-Completion Notice, not issuing a further one after an extension of time, deducting without a valid Pay Less Notice, and calculating from the wrong Completion Date. Each can turn a sound claim into an order to repay.
For contractors, the same sequence is a checklist for challenging a deduction. If a notice is missing or late, the notified sum may be payable in full, leaving the employer to pursue the delay separately. Many contracts amend these clauses, so the notices required will depend on the contract as signed.
What we would suggest checking
Before deducting or challenging liquidated damages, we would suggest checking:
- Contract Particulars: the rate, the period it applies to and any Sections;
- Completion Date: that every extension of time has been decided and the date is correctly calculated;
- Non-Completion Notice: that one was issued after the Completion Date passed, and reissued after any later Completion Date was fixed;
- Clause 2.29.1 notice: that it was given before the due date for the final payment;
- Clause 2.29.2 notice: that it states whether payment is required or the damages will be deducted, with the rate and period;
- Pay Less Notice: that one was given in time for each payment from which liquidated damages are deducted;
- Service: that each notice was sent by a permitted method to the address in the Contract Particulars; and
- Amendments: how any bespoke amendments change clauses 2.28, 2.29 or 4.10.
If you would like help with a liquidated damages claim, or with notices under a JCT contract, please do not hesitate to contact us.
This article is general information about the JCT Design and Build Contract 2024, not legal advice on any particular situation.
More insights
TCC sends freeholder’s termination of a building safety remediation agreement to trial
A freeholder terminated a developer’s remediation agreement for delay two days after telling a tribunal it should keep working with it. The TCC refused summary judgment: the pressure of a remediation order does not of itself change the test for repudiation.
Read the case noteTCC: draft final account was not the Final Statement; prior correspondence was not notice
A contractor's draft final account was not its Final Statement under an amended JCT Design and Build Contract 2016. Correspondence before the Final Statement was issued could not be notice disputing it, so the employer's objections from 2022 did not count.
Read the case noteTCC refuses to enforce NEC adjudication decision that took a route neither side argued
An adjudicator upheld an NEC compensation event claim on a clause neither party invoked and a programme neither party treated as accepted. The TCC refused summary judgment: so material a point should have been put to the parties first.
Read the case note