Case note · Technology and Construction Court · [2026] EWHC 1404 (TCC)
TCC refuses to enforce NEC adjudication decision that took a route neither side argued
An adjudicator upheld an NEC compensation event claim on a clause neither party invoked and a programme neither party treated as accepted. The TCC refused summary judgment: so material a point should have been put to the parties first.
On 10 June 2026, Adrian Williamson KC, sitting as a Deputy Judge of the High Court, handed down judgment in the Technology and Construction Court (TCC) in Premier Modular Ltd v Maidstone and Tunbridge Wells NHS Trust [2026] EWHC 1404 (TCC). He dismissed the contractor’s application for summary judgment to enforce an adjudicator’s re-corrected decision, issued on 26 February 2026, awarding it £1,655,385.49 and other relief, holding that the employer had shown a real prospect of succeeding on its contention that the decision was arrived at in breach of the rules of natural justice (at [48]–[51]).
For NEC users, the case illustrates how much can turn on which programme is the Accepted Programme; for anyone running or deciding an adjudication, it shows what can happen when an adjudicator resolves a central issue by a route neither party argued and never puts it to them.
Background
Premier Modular Ltd (PML) agreed to design and construct a new barn theatre on the Maidstone Hospital site for Maidstone and Tunbridge Wells NHS Trust (the Trust). The contract, dated 3 August 2023, was based on NEC4 Option A (priced contract with activity schedule) (at [11]). PML asserted that it needed the permanent mains water supply made available no later than 30 October 2023 and that the Trust failed to make it available until 20 February 2024, causing delay. The Trust’s position was that it was responsible for the supply, but that there was no requirement for it to be made available by any particular date (at [13]).
Under clause 11.2(1), the Accepted Programme was the programme identified in the Contract Data or “the latest programme accepted by the Project Manager”; here, that was the contract programme at Appendix 3. It was common ground before the court that the Project Manager never accepted a later programme, and that the contract programme contained no obligation on the Trust to provide permanent water by any particular date, although various later programmes PML put forward did (at [14]). Clause 60.1(3) made it a compensation event if the Client did not provide something which it was to provide “by the date shown on the Accepted Programme” (at [15]).
In the adjudication, PML relied instead on clauses 60.1(1) (an instruction changing the Scope), 60.1(14) (a Client’s liability) and 60.1(18) (a breach of contract by the Client) (at [21]). The Trust denied each, and said that in any event the events under (14) and (18) had not been notified, so PML’s claim was time-barred (at [24]).
The adjudicator’s decision took a different route. He treated Rev 3, a revision PML issued on 30 October 2023, as an Accepted Programme by default: although the procedures were not followed, the Project Manager had not taken steps to reject or amend it. Rev 3 showed the water main as required by 30 October 2023, so the Trust’s failure to provide it by then was a compensation event under clause 60.1(3); and there was no time bar (at [30]–[32]).
The Trust resisted enforcement on three natural justice grounds: the compensation event finding rested on a contractual basis the parties had not raised (ground 1); the adjudicator failed to address its condition precedent defence (ground 2); and his finding that the Accepted Programme had been updated contradicted both parties’ position (ground 3) (at [2]). It also argued, somewhat faintly, that he exceeded his jurisdiction (at [3]).
Grounds 1 and 3: an unargued route, never put to the parties
Taking grounds 1 and 3 together, the judge found that the central issue (whether the water main was supplied on time, giving rise to a compensation event) had been decided on a basis that was not argued by either party, was directly contrary to the common position that the only Accepted Programme was that at Appendix 3 to the contract, and was not put to the parties by the adjudicator (at [35]).
He rejected each of PML’s arguments on ground 1 (at [38]–[39]):
- that the notice of adjudication framed the dispute widely: that would answer a jurisdiction challenge, but not a natural justice complaint;
- that the full list of compensation events in clause 60.1 was before the adjudicator: the parties had addressed clauses 60.1(1), (14) and (18), and if he thought other grounds potentially relevant he should have invited submissions;
- that his clarification question of 22 January 2026 canvassed clause 60.1(3): it referred to that clause, confusingly, but actually asked whether a programme dated 14 July 2023 (Rev 2) was an Accepted Programme, and both parties agreed it was not;
- that, even if not, an adjudicator need not invite submissions on every possible argument: he need not simply accept one side’s submissions, but “if he is to depart from the submissions of both parties, he must ensure that the issues have been fairly canvassed”. That had not happened: the Trust first learned of the clause 60.1(3) case from the decision.
On ground 3, PML said that the adjudicator had to decide which programme to use in assessing delay, and that the parties had disputed it (at [40]). The judge said the first point went to jurisdiction, not natural justice, and the second principally to jurisdiction. As for natural justice, PML’s case for measuring delay against a later, unaccepted programme did not really address the point that, on the existence (not the quantification) of the compensation event, the adjudicator founded his decision on a programme that neither party alleged to be an Accepted Programme (at [41]).
The judge concluded: “This startling conclusion was clearly material to the Decision, and it should have been put to the parties for comment.” Not doing so was a breach of the rules of natural justice: the adjudicator had gone off on a frolic, in effect inventing a case for PML which he considered superior to the one PML had actually advanced (at [42]).
Jurisdiction: within the dispute referred
Finding it unnecessary to delve very far into the point (at [3]), the judge accepted PML’s submissions, including that the dispute was framed widely and required a decision on which programme to use for assessing delay, and held that everything decided was within the scope of the matters referred (at [43]).
Ground 2: a possible misunderstanding is not unfairness
The Trust’s second complaint was that the adjudicator failed to address its defence, argued at length, that the compensation event had not been notified under clause 61.3 (at [45]). The judge held that he had plainly addressed it. He may have misunderstood the Trust’s case, or confused the contract’s early warning regime with clause 61.3, but that is not a breach of the rules of natural justice: “It is not for the court, in enforcement proceedings, to pick over a Decision and consider which parts are correct and which are more doubtful” (at [46]).
Why summary judgment was refused
Under rule 24.3 of the Civil Procedure Rules, the question was, among other things, whether the Trust had no real prospect of succeeding on its defence (at [47]). The judge had said in terms that there was a breach of natural justice (at [42]), but what he decided, applying that test, was that the Trust’s defence enjoyed a real prospect of success (at [48]).
Mindful of the Court of Appeal’s guidance in Carillion v Devonport [2005] EWCA Civ 1358 that courts should interfere with adjudicators’ decisions only in rare circumstances, he found this to be one of the rare cases where there has been obvious unfairness (at [48]–[49]). In his view, the difficulty of deciding substantial disputes in very short order weighs more heavily in favour of enforcement where the complaint is that a point has been overlooked or misunderstood. Here the adjudicator “did not neglect a matter under pressure of time. Rather, he sought to create a case for PML which PML had not made and with which the Trust had no proper opportunity to deal, even by the hectic standards of adjudication” (at [50]).
Comment
The judgment applies settled law. The judge considered that the case fell into the second of two categories of challenge: a decision on a basis the responding party had no adequate opportunity to deal with, as distinct from a failure to consider a defence (at [5]–[6]). He emphasised the test in Cantillon Ltd v Urvasco Ltd [2008] EWHC 282 (TCC) of an adjudicator going off on a frolic of his own (quoted at [6]), and the rule in Roe Brickwork Ltd v Wates Construction Ltd [2013] EWHC 3417 (TCC) that an adjudicator should not decide a point on a factual or legal basis that has not been argued or put forward (quoted at [7]). An adjudicator can still decide a point on the material before him on a basis for which neither party has contended, provided the parties were aware of the relevant material and the issues had been fairly canvassed (quoted at [7]).
In September 2026, enforcing a decision in Coventry & Warwickshire Development Partnership LLP v Avison Young (UK) Ltd [2026] EWHC 2319 (TCC), Eyre J cited the case as illustrating how stark the circumstances must be before the court will find a breach of this kind (at [78]). There, the adjudicator proceeded on a basis both parties had disavowed, but only after forewarning them, explaining why and inviting submissions, so there was no breach (at [81]–[83]).
For NEC users, the Accepted Programme did two jobs here. Under clause 63.5, as PML’s referral quoted it, the Accepted Programme current at the dividing date is the baseline for assessing delay to the Completion Date (at [22]); under clause 60.1(3), it is a compensation event if the Client does not provide something it is to provide by the date the Accepted Programme shows (at [15]). With no water date in the contract programme (at [14]), the adjudicator’s clause 60.1(3) route depended on treating a later programme as accepted.
The merits were untouched. The court made no finding on whether there was a compensation event, on the clause 61.3 time bar, or on whether an early warning notice can serve as notification. Nor did it decide whether a programme can become accepted when the Project Manager takes no steps to reject or amend it; PML had told the adjudicator that the clause 31.3 acceptance mechanism was not operated (at [27]).
Practical takeaways
For contractors
- Make sure any date by which the Client is to provide something is shown on the Accepted Programme, the date clause 60.1(3) looks to (at [15]). Under clause 11.2(1), that is the programme identified in the Contract Data until the Project Manager accepts a later one, and the latest programme accepted supersedes earlier ones (at [26]). Put the dates in from the start, carry them into every revised programme and press for acceptance (clause 31.3 here).
- Run every compensation event head you want the adjudicator to decide, with the programme it depends on, expressly in your own submissions. A broadly drawn notice answered only the jurisdiction challenge here.
For employers and project managers
- Respond formally, within the time the contract allows, to every programme submitted for acceptance (clause 31.3 in this contract). The adjudicator treated a revised programme as accepted by default, since the Project Manager had not taken steps to reject or amend it (at [30]); the court did not rule on whether he was right.
- Separate fairness from error before resisting enforcement: misunderstanding a defence the adjudicator has addressed is not a breach of the rules of natural justice (at [46]); the defence’s merits are a matter for final determination.
For adjudicators
- If you are minded to decide on a ground neither party has run, tell the parties so in terms and invite their submissions before deciding. A question that names a clause but asks about something else may not be enough (at [39]).
What next
We are not aware of any appeal, and it is not known whether permission to appeal was sought. The judgment does not say what will happen to the claim, and the merits remain open.
This article is for general information only and is not legal advice.
More insights
TCC sends freeholder’s termination of a building safety remediation agreement to trial
A freeholder terminated a developer’s remediation agreement for delay two days after telling a tribunal it should keep working with it. The TCC refused summary judgment: the pressure of a remediation order does not of itself change the test for repudiation.
Read the case noteClaiming liquidated damages under the JCT Design and Build Contract 2024
The notices an employer needs to claim liquidated damages under JCT DB 2024, in order: the Non-Completion Notice, the clause 2.29 notices and the Pay Less Notice, with the clauses behind each.
Read the guideTCC: draft final account was not the Final Statement; prior correspondence was not notice
A contractor's draft final account was not its Final Statement under an amended JCT Design and Build Contract 2016. Correspondence before the Final Statement was issued could not be notice disputing it, so the employer's objections from 2022 did not count.
Read the case note