TCC sends freeholder’s termination of a building safety remediation agreement to trial
A freeholder terminated a developer’s remediation agreement for delay two days after telling a tribunal it should keep working with it. The TCC refused summary judgment: the pressure of a remediation order does not of itself change the test for repudiation.
Read the case noteTCC: draft final account was not the Final Statement; prior correspondence was not notice
A contractor's draft final account was not its Final Statement under an amended JCT Design and Build Contract 2016. Correspondence before the Final Statement was issued could not be notice disputing it, so the employer's objections from 2022 did not count.
Read the case noteTCC refuses to enforce NEC adjudication decision that took a route neither side argued
An adjudicator upheld an NEC compensation event claim on a clause neither party invoked and a programme neither party treated as accepted. The TCC refused summary judgment: so material a point should have been put to the parties first.
Read the case noteTCC refuses DHSC summary judgment and strike-out in £15.35m PPE gloves prepayment dispute
DHSC asked a glove supplier for pre-delivery testing beyond what the contracts provided. The supplier can realistically argue that the original delivery dates stopped binding it, and that the repayment clause does not require a refund if DHSC's breach caused the non-delivery.
Read the case noteTCC refuses to strike out owner’s DPA claim after parent lost on limitation
A developer’s Defective Premises Act claim failed in arbitration as time-barred, weeks before the Building Safety Act extended limitation. The High Court has held that its subsidiary, which acquired an interest in the development, may still bring its own claim for largely the same defects.
Read the case noteTCC refuses to stop US$484 million bond call for disputed delay liquidated damages
Arguments that delay liquidated damages were a penalty, or not due because of extensions of time, did not justify an injunction: fraud aside, interim relief requires it to be clearly established that the contract precludes the call. The penalty point was not finally decided.
Read the case note