Case note · Technology and Construction Court · [2026] EWHC 2003 (TCC)
TCC sends freeholder’s termination of a building safety remediation agreement to trial
A freeholder terminated a developer’s remediation agreement for delay two days after telling a tribunal it should keep working with it. The TCC refused summary judgment: the pressure of a remediation order does not of itself change the test for repudiation.
On 30 July 2026, Mr Justice Constable handed down judgment in the Technology and Construction Court (TCC) in Durkan Estates Ltd v Wallace Estates Ltd [2026] EWHC 2003 (TCC). He dismissed the freeholder’s application for summary judgment on its termination of a remediation agreement, under which the developer of Centrillion Point in Croydon had agreed to remedy building safety defects at its own cost. Whether the termination was lawful will be decided at trial.
For freeholders under a remediation order, the deadline does not lower the bar for terminating for delay, and what they tell the tribunal may be used against them. For developers doing the work, the case shows why programme changes should be recorded properly.
Background
Durkan Estates Ltd (Durkan) converted Centrillion Point, a former office building, into dwellings in the late 2000s. Wallace Estates Ltd (Wallace) has owned the freehold since 2014. On 4 January 2024, on the leaseholders’ application, the First-tier Tribunal (FTT) made a remediation order under s.123 of the Building Safety Act 2022 (BSA) requiring Wallace to remedy relevant defects by 31 May 2025.
Under an agreement of 1 July 2024, Durkan agreed to design and carry out the works for no fee. Completion was due by 19 September 2025 “or such other date as is agreed as part of the Plans and Specifications”, already after the order’s deadline, and work could not start until the Building Safety Regulator (BSR) gave building control approval at Gateway 2. Time was not of the essence. A remediable breach only became a “Substantive Breach”, justifying termination on 14 days’ notice, if it was notified and not remedied within a reasonable period. By clause 11.2, no affirmation by Wallace was effective “unless it is in writing”, and writing excluded email.
On 24 June 2025 the FTT refused to extend the order’s deadline; no Gateway 2 application had been made. At that hearing, which Durkan attended, Wallace’s counsel said Wallace “took the view that it should continue working with Durkan to progress the remediations” (at [62]). Two days later Wallace terminated, under the agreement and at common law.
Wallace then applied to the FTT for a remediation contribution order (RCO) under s.124 of the BSA against Durkan and its parent, currently estimated at about £13.6 million. Durkan opposes it and says any order should not exceed about £6.7 million, its cost of finishing the works. Durkan also sued in the TCC for a declaration that the termination was unlawful. Wallace sought summary judgment (judgment without a trial), but only on its case that Durkan was in repudiatory or anticipatory breach at common law: a breach serious enough to entitle Wallace to end the agreement.
Had the completion date moved?
Wallace said Durkan had not even taken the steps needed to start work, so completion by 19 September 2025 was out of reach. Durkan said the parties had worked to an undated programme allowing 68 weeks’ construction from BSR approval, and that Wallace knew the September date would not be met. The date had therefore moved under the agreement or by estoppel by convention (a shared assumption on which both parties acted).
The judge saw force in Wallace’s reply that the date could only change through the agreement’s formal approval procedure, but did not decide it, because it did not answer the estoppel case. It was plainly arguable that nobody expected completion by 19 September 2025 or treated the date as contractually significant (at [43]). If Wallace was estopped from relying on it, the anticipatory breach case would fall away, and that could not be decided without a trial and disclosure (at [44]).
A remediation order does not change the test for repudiation
With time not of the essence and no notice making it so, Wallace had to show delay that deprived it of substantially the whole benefit of the agreement: the same test as for frustration, and a high bar (at [46]).
Wallace argued that the risk of its directors facing committal for breaching the order made the delay repudiatory without more. The judge disagreed. On its own case, Wallace had signed an agreement that already carried that risk, and the order raised the stakes without changing the test: “Whilst the Building Safety Act context and the RO materially increase the importance of timely performance, they do not of and in themselves alter the test for repudiation nor convert a non-essential time stipulation into a condition” (at [49]).
Why the delay happened was disputed, and Durkan’s case that Wallace contributed to it had the support of independent expert evidence (at [50]). Wallace’s reply, that particular clauses made the causes irrelevant, was unpleaded: “A pleading is not required to argue the law: it must plead the facts relied upon” (at [51]). Such points could not fairly be raised for the first time in oral argument and, even if pleaded, would not have allowed summary disposal (at [52]).
Other matters needed a trial too: whether Durkan was making an effort to perform (Shawton Engineering Ltd v DGP International Ltd [2006] BLR 1); whether the delay was remediable, given expert evidence that the Gateway 2 submission could have been made within 8 to 10 weeks of termination, when Wallace’s replacement contractor took many months; and whether Wallace’s lack of complaint showed that timing was not central to it (at [53]–[56]).
Affirmation at the tribunal
Durkan also says Wallace affirmed the agreement (chose to keep it alive, giving up the right to end it for breaches it knew of) at the 24 June hearing. Wallace’s skeleton argument said termination would not solve the problem and that Durkan was close to making its Gateway 2 application, and a Wallace witness said handing the project to another firm would only delay the start on site. Wallace had offered no explanation for its change of position two days later (at [64]).
Statements made to the tribunal rather than to Durkan could still count, not least because Durkan was present (at [66]). As for clause 11.2, it was reasonably arguable that its first sentence does not concern election, and that written submissions to a court, made to the other party’s knowledge and unequivocally showing an intention to continue, could be an affirmation in writing (at [67]). Clause 11.2 was no knock-out answer. Whether continuing delay gave a renewed right to terminate two days later is also for trial (at [68]).
The first joint hearing of the TCC and the FTT
On 31 July 2026, Mr Justice Constable sat with Judge Siobhan McGrath, President of the FTT’s Property Chamber, in the first joint hearing of the TCC and the FTT. Their short judgment, Wallace Estates Ltd v Durkan Estates Ltd [2026] EWHC 2133 (TCC), gives initial guidance. The parties had agreed that the RCO application and the TCC claim should be managed and tried together, following the approach in section 9 of the new Fourth Edition of the TCC Guide, although this claim was outside its strict terms (at [15]).
The agreed order is a useful template (at [24]–[38]): one set of witness statements and one set of expert evidence (architecture, fire engineering and quantity surveying) under the CPR; extended disclosure under Practice Direction 57AD, usable in both sets of proceedings; findings of fact binding in both and on all three parties; and separate cost codes, because the FTT is in essence a no-costs jurisdiction. A TCC judge and an FTT judge will hear the trial, without a professional member (at [26]–[28]). Whether the FTT could itself rule on the termination was expressly left open (at [23]).
Comment
Nothing here changes the law on termination for delay. The judgment applies settled principles, from Hongkong Fir to Ampurius Nu Homes v Telford Homes, where the pressure to finish is unusually acute. A freeholder facing a remediation order deadline and possible committal will feel that every week matters, but greater urgency does not lower the bar for terminating.
The agreement’s own machinery mattered too. Where the parties have agreed that remediable breaches need notice and a chance to cure, a breach of that kind without notice is unlikely to be repudiatory on its own (at [24], drawing on BSkyB Ltd v HP Enterprise Services UK Ltd [2010] EWHC 86 (TCC)).
The affirmation point is the most practical. A freeholder seeking more time from the FTT will naturally present the remediation as a joint effort that is nearly there. If it then terminates, those statements may become the developer’s best evidence, and a standard non-waiver clause may not neutralise them.
Two limits matter:
- Nothing has been decided on the merits. The court held only that Durkan’s claim that the termination was unlawful has a real prospect of success (at [69]).
- The contractual route was not argued. Wallace’s application was confined to common law repudiation; its case on “Substantive Breach” under the agreement was not before the court.
Practical takeaways
For freeholders and others under a remediation order
- Align the agreement with the order, including what happens if the tribunal will not extend the deadline.
- If a date really matters, make it of the essence expressly; otherwise use the notice-to-cure procedure before terminating for delay.
- Keep what you tell the tribunal consistent with your contractual position, and reserve your rights in writing if termination is in prospect.
- Plead the clauses you rely on to answer the other side’s case on the causes of delay.
For developers and contractors carrying out remediation
- Record changes to the programme and completion date in the form the agreement requires; here, writing excluded email.
- Give notice of delay events under the extension of time procedure, even while relations are good.
- Keep records of the other side’s part in design review, appointments and access.
For both
- Where FTT and TCC proceedings overlap, apply early for joint case management under section 9 of the TCC Guide.
What next
The lawfulness of the termination and the RCO application, including its amount, will be decided together at a joint trial listed from 31 January 2028, with a back-up listing from 11 October 2027 if court time becomes available. The parties agreed in principle to mediate in August or September 2026. It is not known whether permission to appeal has been sought.
This article is for general information only and is not legal advice.
More insights
Claiming liquidated damages under the JCT Design and Build Contract 2024
The notices an employer needs to claim liquidated damages under JCT DB 2024, in order: the Non-Completion Notice, the clause 2.29 notices and the Pay Less Notice, with the clauses behind each.
Read the guideTCC: draft final account was not the Final Statement; prior correspondence was not notice
A contractor's draft final account was not its Final Statement under an amended JCT Design and Build Contract 2016. Correspondence before the Final Statement was issued could not be notice disputing it, so the employer's objections from 2022 did not count.
Read the case noteTCC refuses to enforce NEC adjudication decision that took a route neither side argued
An adjudicator upheld an NEC compensation event claim on a clause neither party invoked and a programme neither party treated as accepted. The TCC refused summary judgment: so material a point should have been put to the parties first.
Read the case note