Case note · Technology and Construction Court · [2026] EWHC 1530 (TCC)

TCC: draft final account was not the Final Statement; prior correspondence was not notice

A contractor's draft final account was not its Final Statement under an amended JCT Design and Build Contract 2016. Correspondence before the Final Statement was issued could not be notice disputing it, so the employer's objections from 2022 did not count.

On 23 June 2026, Jonathan Acton Davis KC, sitting as a Deputy Judge of the High Court, handed down judgment in the Technology and Construction Court (TCC) in Oakland Wantage Care Home Ltd v Stepnell Ltd [2026] EWHC 1530 (TCC). He refused the declarations sought by the employer, Oakland Wantage Care Home Ltd (Oakland), against its contractor, Stepnell Ltd (Stepnell): Stepnell’s February 2022 draft final account was not its Final Statement, and correspondence before its February 2024 statement, the relevant statement, could not be notice disputing it.

For employers, under a clause in this form, a dispute raised only in negotiations must be raised again after the Final Statement is given: by notice before the due date, or by proceedings started within 28 days of its issue (clause 1.8.2). For contractors, a document’s status turns on how a reasonable recipient would read it, not on what the sender privately intended or believed.

Background

By a contract dated 9 August 2019, Stepnell undertook the design and construction of a 65-bed care home at Grove Road, Wantage, for Oakland. The contract was the JCT Design and Build Contract (2016 edition) with bespoke amendments (at [1]–[2]). The works were certified as practically complete on 26 April 2021, which started a 12-month rectification period (at [3]).

On 17 February 2022 Stepnell emailed the employer’s agent (EA) a document (the February 2022 Statement) with a valuation amounting to £8,547,434.96 (at [4], [25]). On 7 March 2022 the EA disputed the sums claimed and found the final account figure to be £7,988,593.74 excluding VAT (the March 2022 Response) (at [5]). Stepnell sent a further statement on 9 February 2024 (the February 2024 Statement) (at [6]).

Stepnell referred a dispute to adjudication on 25 March 2024. The adjudicator decided that the relevant statement for clause 4.24.6 was the February 2024 Statement, that no Final Payment Notice or Pay Less Notice (notices of the sum the employer considers due, or of an intention to pay less) had been issued in response, and so the sum it set out was due (at [7]–[8]). Oakland paid the sums found due on 29 May 2024 (at [9]).

On 10 September 2025 Oakland issued a claim under Part 8 of the Civil Procedure Rules (CPR), the procedure for questions unlikely to involve a substantial dispute of fact. It sought declarations that the February 2022 Statement was the relevant statement and that it had disputed it, or alternatively that it had disputed the sums in the February 2024 Statement; that the relevant statement was therefore not conclusive as to the sum due; and that it was entitled to adjudicate or litigate the true value of Stepnell’s final account (at [10], [52]).

The final account clauses in this contract

The judgment quotes clauses 4.24 and 1.8 (at [13]–[14]) but does not say whether they were among the amendments. Clause 4.24.5 fixes the due date for the final payment one month after whichever is last of: the end of the rectification period; the date stated in the notice of completion of making good; and the submission of the contractor’s Final Statement or, if issued first, an Employer’s Final Statement (the relevant statement).

Under clause 4.24.6, except to the extent that the employer gives notice before the due date “disputing anything in the Final Statement”, and subject to clause 1.8.2, the relevant statement becomes conclusive on the due date as to the sum due. Clause 1.8.1 adds that it is then conclusive evidence in any proceedings that, among other things, the extensions of time given under clause 2.25 are “all and only” those due, and that the reimbursement of loss and expense agreed, ascertained or valued under the contract is in final settlement of all the contractor’s claims arising out of Relevant Matters.

Under clause 1.8.2, proceedings commenced before or within 28 days after the statement’s issue suspend those effects as to their subject matter until they conclude, after which the outcome governs. If an adjudication started in that window is decided after the statement’s issue, follow-on arbitration or litigation is protected only if started within 28 days of the decision (clause 1.8.2.2), and proceedings with no further step by either party in any 12-month period starting on or after the statement’s issue are treated as concluded (clause 1.8.3).

Was the February 2022 document Stepnell’s Final Statement?

It was common ground that the test was objective: how a reasonable recipient, placed as the parties were and taken to know the contract, would have read the document, applying Advance JV v Enisca Ltd [2022] EWHC 1152 (TCC) (at [21]–[22]).

Oakland’s case was that it was the Final Statement and that its March 2022 Response, or alternatively a September 2022 document, disputed it in time (at [16]). It relied on the negotiations, a covering email calling it the final account, its statement of the sum due and its basis, the lack of any labelling requirement and the EA’s formal response (at [23]–[28]). Stepnell, which had sent it, disagreed (at [29]–[30]).

The judge rejected two of Stepnell’s subsidiary arguments: that the document should be tested against the parties’ subjective understanding, as it appeared from their February and March 2022 correspondence, since that was inconsistent with the objective test (at [22], [31]); and that the adjudicator’s view was a useful touchstone, since “An Adjudicator, however experienced, is not necessarily the objective reasonable recipient” (at [32]).

But he accepted Stepnell’s reasons based on the document itself (at [30], [34]). Read as a whole it was a draft or forecast, headed as a draft final account; particular figures were draft, budget or estimate; and a final account with finalised figures and further particulars was still to come. “It may well be that Stepnell intended to send, and perhaps even believed, that the February 2022 Statement was the Final Statement under clause 4.24 of the Contract” (at [34]). But in view of those factors, a reasonable recipient in context would not have treated it as such (at [34]).

The judge therefore did not need to decide whether Oakland had disputed it in time (at [35]). It followed that the February 2024 Statement was the relevant statement (at [36]).

Notice must follow the Final Statement

Oakland’s alternative case was that it had given notice disputing the sums in the February 2024 Statement before the due date: in the 2022 discussions, including the March 2022 Response and the September 2022 document, and as recorded in that statement itself (at [17], [37], [46]). It argued that clause 4.24.6 does not expressly rule out earlier notice, so long as the other party is on notice of the underlying dispute before the due date (at [44]–[45]). That reading, it said, fitted clause 1.8.2.1 and struck the “right balance” described in Battersea Project Phase 2 v QFS Scaffolding (2024), a decision on a different point under a JCT subcontract (at [41]–[47]).

The judge disagreed: to avoid conclusivity, the employer must give notice disputing anything “in” the Final Statement (at [49]). “It must be a pre-condition to that notice that the Final Statement shall first have been given. It follows that correspondence prior to the issue of a Final Statement is not notice for the purposes of clause 4.24.6” (at [50]). So notice can only follow the Final Statement, and must come before the due date.

Oakland therefore also failed on the second issue, whether the relevant statement had become conclusive and had the further effects stated in clause 1.8 (at [18], [51]). The judge noted that the clause uses the same preposition for a contractor’s notice disputing an Employer’s Final Statement (at [49]).

No declarations for either side

Oakland’s declarations were refused (at [52]). Stepnell’s counsel had sought declarations in his skeleton argument but conceded that without a pleading or an application notice the court had no jurisdiction to make them (at [52]). So the judgment grants no declaration that the February 2024 Statement was conclusive.

Comment

On the first issue the court applied settled principles, and the document’s own features were decisive: labels and forecasts natural in a negotiating document can stop it being the Final Statement.

The notice point turns on the word “in”, and the judge’s reading is the natural one: a notice cannot dispute the contents of a document that does not yet exist.

The reasoning does not engage expressly with clause 1.8.2.1 or Battersea, although Oakland’s point had some force: that clause gives effect to proceedings commenced before the statement is issued. The distinction is defensible, since proceedings have a defined subject matter, while a notice disputing “anything in” a statement can only respond to what it contains.

Two limits matter:

  • Some points were not addressed. The judgment does not deal expressly with what the February 2024 Statement itself recorded, or with the Final Payment Notice listed in the claim form (at [10]), and records no argument that clause 1.8.2 suspended that statement’s effects: the only proceedings it mentions began more than 28 days after it (at [6]–[7], [10]).
  • Clause 1.8.1 was not applied. The court did not consider what a conclusive statement meant here for extensions of time or loss and expense; the effects described above are those of the contract’s wording.

Practical takeaways

For employers and employer’s agents

  • Respond to the Final Statement itself: once it has been issued, and before the due date (possibly only a month after submission: clause 4.24.5), serve a notice disputing everything in it that you dispute. A notice disputing the statement is not, as such, a Final Payment Notice or Pay Less Notice, so also serve any the contract requires, on time: the adjudication here turned on their absence (at [7]–[8]).
  • Dispute any document that might be the Final Statement, even if you think an earlier one was. If a dispute is already live, consider starting proceedings within the clause 1.8.2 window, which can close before the due date, and pursuing them; the court’s reasoning does not address clause 1.8.2.

For contractors

  • Make a Final Statement final on its face: identify it as such, include everything clause 4.24.2 requires, and leave out draft labels, forecasts, budget figures and promises of further particulars.
  • Put all your loss and expense in the Final Statement, and get every extension of time you need granted before submitting it: the statement becomes conclusive on the due date (clause 1.8.1), but the window for proceedings closes 28 days after its issue. You cannot dispute your own statement by notice (clause 4.24.6), so for anything still disputed, start proceedings within that window, and pursue them (clauses 1.8.2 and 1.8.3).

For both

  • Check the wording of your own contract and its amendments. JCT’s published contents page shows that the 2024 edition still has clauses 1.8 (Effect of Final Statement) and 4.24 (Final Statement and Final Payment).
  • If you defend a Part 8 claim and want declarations of your own, state the remedy in your acknowledgment of service (CPR 8.3(2)(b)) and seek permission to counterclaim (CPR 8.7), or issue your own claim.

What next

The judgment does not mention permission to appeal, and no appeal or later judgment has been reported. Costs were left for agreement or a further hearing or decision on paper (at [53]).


This article is for general information only and is not legal advice.