Case note · Technology and Construction Court · [2026] EWHC 561 (TCC)

TCC refuses DHSC summary judgment and strike-out in £15.35m PPE gloves prepayment dispute

DHSC asked a glove supplier for pre-delivery testing beyond what the contracts provided. The supplier can realistically argue that the original delivery dates stopped binding it, and that the repayment clause does not require a refund if DHSC's breach caused the non-delivery.

On 12 March 2026, Mr Justice Constable handed down judgment in the Technology and Construction Court (TCC) in UK Global Healthcare Ltd v Secretary of State for Health and Social Care [2026] EWHC 561 (TCC). He dismissed an application by the Secretary of State (DHSC) for summary judgment (judgment without a trial) on a counterclaim for the return of £15.35 million (plus interest) paid in advance for medical gloves, and to strike out the supplier’s claim.

On an argument the supplier had not pleaded, the judge accepted that the prevention principle, familiar from building contracts, arguably applied to these supply contracts: a point for suppliers asked to go beyond their contracts, and for purchasers who ask.

Background

In contracts dated 27 May and 8 June 2020, UK Global Healthcare Ltd (UKGH) agreed to supply DHSC with 320 million nitrile examination gloves: 120 million by 30 June 2020 and the rest by 31 July 2020. Time was of the essence, and a missed delivery date was deemed a breach incapable of remedy for the purposes of termination. DHSC paid £15.35 million in advance, but no gloves have been delivered (at [4]–[9]).

In June 2020 DHSC sought pre-delivery testing to recognised standards, which UKGH tried to accommodate (at [43]–[56]). DHSC later refused the gloves after laboratory testing that UKGH says was flawed (at [65]–[70]). By a letter dated 28 October 2020 DHSC purported to terminate, on grounds it now accepts were not valid (at [4]). It relies instead on the missed delivery dates, as a good reason that existed at the time, and alternatively on the contracts’ expiry and the repayment clause (at [80]). Waiver can qualify the good-reason principle only where it amounts, in effect, to estoppel (at [29]).

Could DHSC still rely on the delivery dates?

UKGH’s pleaded breaches were the rejections, not the requests for testing; its counsel could not identify any clause the requests broke (at [81]). The rejections came after 30 June 2020, so they could not have caused the missed 30 June deliveries, though they could have caused the missed 31 July dates; the judge took events in order, starting before 30 June (at [82]–[83]).

He held that UKGH has a real prospect of establishing at trial that DHSC agreed to extend the delivery dates, waived compliance or is estopped from relying upon them (at [84]). In summary (at [85]):

  • DHSC conceded that the contracts gave it no right to have the gloves due on 30 June inspected or tested, and that it could reject goods after testing only once they were delivered (clause 4.2 of Schedule 2). For the later phases, it arguably had no right beyond a visual check of provenance and availability.
  • DHSC arguably sought more intrusive testing before delivery; whether it demanded or requested it did not matter analytically and, if it did, would be for trial.
  • UKGH accommodated the requests, though probably entitled to decline them and simply deliver, but arguably only on terms, made plain in its letter of 23 June 2020 claiming an extension of time (at [55]): the testing was extra-contractual, complying would affect its ability to deliver on time, and a formal variation extending time was required.
  • DHSC could have rejected those conditions. Instead Mick Corti, a procurement lead for gloves in DHSC’s network of NHS Trust leads, replied the same day that it made “total sense to vary the original dates in the contract” (at [56]).
  • UKGH’s director was arguably objectively justified in understanding that by late June DHSC would not hold UKGH to the dates and would formalise new ones; and UKGH arguably relied on that, and on later exchanges saying the amendment was in hand, by spending resources on the extra checks.

If so, UKGH would have a reasonable argument that the parties agreed, though not as clause 17.2 required, to extend the dates by a reasonable time, or that DHSC waived strict compliance or is estopped from relying on the dates to terminate (at [86]).

Clause 17.2 made a variation binding only once agreed in writing and signed on behalf of both parties (at [10]); none ever was (at [20]), and UKGH relies on estoppel to get past the clause (at [21]). Estoppel against such a clause needs, at the least, an unequivocal representation that the variation is valid despite its informality, and “something more” than the informal agreement itself (Rock Advertising (2018)); a representation that the change would be confirmed in writing may supply it (at [22]–[24]). On the authorities DHSC cited, the no-waiver clauses (26.3 and 26.4) likewise raise the bar for waiver without excluding it (at [26]–[27]). On UKGH’s facts, the judge found a real prospect of that something more, for clause 17.2 and, by analogy, the no-waiver clauses, in both parties’ explicit recognition in late June, in particular on 23 June 2020, that the dates needed extending and that this would have to be formalised contractually (at [86]).

Could complying with the requests set time at large?

UKGH also argued, without having pleaded it, that DHSC’s conduct put time at large (at [31]). The prevention principle, as approved in Trollope & Colls (1973), stops a party insisting on a deadline that its own conduct has made impossible or impracticable to meet (at [32]); and “It is well established that actions by the promisee which are perfectly legitimate under a contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date” (at [33]). Time is not set at large, though, where the contract has an extension-of-time mechanism covering the event (Multiplex v Honeywell (2007)), and nobody suggested that these contracts did (at [33]).

The judge held that this further route also has a real prospect of success. He accepted that DHSC was entitled to request pre-delivery testing to which it had no contractual right, on a basis he left open; but if, as a matter of fact, complying made the deadlines impossible to meet, that was arguably an act of prevention. With no contractual mechanism for extending time, time arguably ceased to be of the essence and became at large, in which case DHSC could not justify the termination by pointing to the missed deadlines. UKGH may need to amend, but it would be proper to allow that rather than strike out the claim or give summary judgment (at [87]). The judge had observed that UKGH’s evidence of impossibility was, arithmetically, plainly true for the 30 June deliveries (at [47]).

Rejection, termination and damages

Even if he was wrong about the delivery dates, the judge held that there is a real prospect of UKGH establishing that DHSC rejected the gloves on 21 July 2020, or refused to reconsider when shown passing results; that the testing it relied on was flawed, leaving no objective basis for refusal; and/or that it failed to co-operate over alternative gloves, in particular from Hartalega, by not providing the authorisation needed for their certification, in breach of clause 5.4 of Schedule 2 (at [88]). DHSC did not dispute that the testing point was triable (at [71]). Its main answer, that UKGH had agreed to forgo the original gloves, was not fatal, at least on the application: that agreement arguably rested on flawed testing, and was not unreserved, as UKGH pressed for the final laboratory report and produced passing results (at [89]).

On either route, the termination was arguably unlawful (at [90]). UKGH has not accepted the repudiation, saying the contracts remain on foot because the expiry dates were also waived. But DHSC accepted that a wrongful termination would be repudiatory and could still sound in damages, and did not dispute that loss, including lost profits put at £11.3 million, was triable if breach was (at [91]–[92]).

Does the repayment clause apply where the buyer’s breach caused non-delivery?

Under clause 13.1 the supplier had to reimburse charges, advance payments included, for goods undelivered at expiry or termination (at [10]). The expiry dates had passed without delivery, and DHSC said the clause operated mechanistically (at [96]–[97]).

UKGH relied on what it called the prevention principle of interpretation: wherever possible, a contract is construed so that neither party can profit from its own breach (Carlton Vale v Gapper (2023), drawing on Alghussein v Eton College (1988)). As DHSC stressed, the principle applies only where the breach is causally linked to the right asserted, and express terms, or the intentions they show, can displace it (at [30]). The judge held that UKGH has a reasonable prospect of arguing that, so construed, clause 13.1 imposes no duty to reimburse where a breach by DHSC caused the non-delivery. The opposite reading would on the face of it be exceptional, letting DHSC recover sums that, on unchallenged evidence, may well have been committed in the supply chain; and “Such a construction would need the clearest of words, which do not exist”. The narrower reading met the causation requirement and clashed with no other express term (at [99]).

Even if that were wrong and, subject to waiver, DHSC were entitled to repayment, UKGH’s triable damages claim may equal or exceed the counterclaim; equitable set-off was the obvious question, but it was neither pleaded nor argued, so the judge went no further (at [100]). He did not decide whether UKGH’s waiver case reaches the expiry dates, though he saw force in DHSC’s complaint that it was deficient in pleading and evidence: nothing in the documents suggested the parties had turned their minds to those dates as they had to the delivery dates, and an act of prevention delaying a delivery date need not affect a date serving a different purpose. Despite his scepticism, with a trial to come anyway, he would not strike it out (at [101]–[102]).

Comment

Nothing here changes the law, and nothing has been decided on the merits. For anyone following the prevention principle, the main point is that two different rules are in play. The time-at-large principle can be triggered by legitimate conduct, but is excluded by a contractual mechanism for extending time for the event in question. The interpretive principle applied to clause 13.1 needs a breach that caused the outcome, and here only “the clearest of words” could have overridden it (at [99]). So the testing requests alone would not seem enough for the clause 13.1 argument: UKGH will need to show that a breach, such as a wrongful rejection or a failure to co-operate, caused the non-delivery.

Practical takeaways

For suppliers and contractors

  • Use the contract’s machinery, or put conditions in writing. If your contract has an extension-of-time procedure, use it and give its notices on time; a missed notice may cost you the extension without setting time at large (Multiplex v Honeywell (2007)). If it has none, as here, record at the time that the requests go beyond the contract, will affect the dates and need a formal variation, as UKGH arguably did (at [85]–[86]), then get it signed.
  • Check whether you must comply. The judge accepted that UKGH was probably entitled to decline the testing and simply deliver (at [85]), though DHSC arguably made clear that the gloves should not be shipped meanwhile (at [52]); whether you are entitled depends on your own contract’s testing terms.

For employers and public-sector purchasers

  • Write in the testing you need. Provide for any pre-delivery testing you may want, with a mechanism to extend the delivery dates for delay it causes. Without one, an act of prevention may set time at large (at [33]), leaving a duty to perform within a reasonable time (Multiplex v Honeywell (2007)).
  • Answer conditions expressly. If a supplier makes compliance conditional on new dates, reject the condition or record the new dates as the contract requires; DHSC did not reject the condition (at [85]) and signed no variation (at [20]). A signed-variation clause may not protect you if you agree that the dates should change, say the change will be formalised and let the supplier act on that (at [84]–[86]).
  • Say what happens to advance payments. If an advance is to be repayable even where you are said to have caused the non-delivery, say so expressly: these contracts allowed recovery under their terms where goods were rejected or on expiry or termination (at [7]–[8]), yet the judge found the clearest words lacking (at [99]). A connected damages claim may also raise equitable set-off, a question the judge noted but left open because it was neither pleaded nor argued (at [100]).

What next

The claim and counterclaim go to trial on all these issues, including the second contract’s disputed expiry date and any waiver of the expiry dates. UKGH may need to amend to plead prevention, if it has not already done so. No appeal has been reported.


This article is for general information only and is not legal advice.