Case note · Technology and Construction Court · [2026] EWHC 2047 (TCC)
TCC refuses to stop US$484 million bond call for disputed delay liquidated damages
Arguments that delay liquidated damages were a penalty, or not due because of extensions of time, did not justify an injunction: fraud aside, interim relief requires it to be clearly established that the contract precludes the call. The penalty point was not finally decided.
On 4 August 2026, Mr Justice Pepperall handed down judgment in the Technology and Construction Court (TCC) in TTSJV W.L.L. & Ors v BapCo Refining B.S.C. (Closed) [2026] EWHC 2047 (TCC). He gave his reasons for refusing an injunction to stop BapCo pursuing a US$484.4 million demand on a performance guarantee for delay liquidated damages, having indicated soon after the 22 May 2026 hearing that the application would be dismissed.
For employers and contractors on engineering, procurement and construction (EPC) and other major projects, the case shows how hard it is to stop a call by disputing liquidated damages.
Background
Under a 2018 EPC contract, later novated to the joint venture vehicle TTSJV W.L.L. (TTSJV), a consortium was to design, engineer, procure, construct, test and complete the modernisation of BapCo’s existing oil refinery in Bahrain, for US$4.211 billion. TTSJV’s parent companies joined the application to fortify its cross-undertaking in damages (at [3]–[5]).
The law of England and Wales governed the contract, and disputes went to binding arbitration under the rules of the London Court of International Arbitration (LCIA), seated in London (at [4]). The LCIA has developed procedures for appointing an emergency arbitrator in cases of exceptional urgency (at [11]).
BapCo says TTSJV failed to achieve milestone 12 by 26 October 2025, and by the hearing it claimed US$484,406,323, the cap on liquidated damages at 10% of the adjusted contract price (at [6.1]). TTSJV claims extensions of time for delay following an explosion on 2 May 2025 that killed three workers, for which it contends BapCo was responsible (at [6.2]).
On 21 May 2026 BapCo called on the guarantee, issued by HSBC Bank Middle East Ltd (at [1], [7]). TTSJV asked the LCIA to appoint an emergency arbitrator that day, concerned that HSBC would be likely to pay before Eid began on 25 May and before one could be appointed (at [7]). It sought an injunction requiring BapCo to suspend the demand and restraining further demands on the guarantee or a Mashreqbank retention bond (at [1]).
The court could act ahead of an emergency arbitrator
Under section 44(5) of the Arbitration Act 1996, as amended for arbitrations begun on or after 1 August 2025, the court acts only if or to the extent that the tribunal or emergency arbitrator, and any arbitral or other institution or person vested by the parties with power in that regard, has no power or is unable for the time being to act effectively (at [10]).
Given the terms of the bond, the judge found a very real prospect that the funds would be released before an emergency arbitrator could be appointed and grant effective relief, so the court should entertain the application despite s.44(5). Any relief would only have preserved the position temporarily, until the emergency arbitrator could act (at [11]).
The test: clearly establishing that the contract precludes the call
Absent fraud, the court will not restrain a bank from paying a demand that complies with the bond, but the beneficiary itself may be restrained from calling where the contract clearly precludes the call (at [16]–[21]). In Sirius v FAI (2003), the Court of Appeal accepted that a contractual undertaking not to draw on a letter of credit without written consent could be enforced by injunction where the beneficiary was positively shown not to be entitled to draw (at [20]); those remarks were obiter, as the money was already in escrow (Sirius at [28]–[29]).
TTSJV argued that a strongly arguable case that the contract barred the call was enough (at [13]). Pepperall J applied the stricter test: a seriously arguable case of breach of the underlying contract is not sufficient, and relief “can only be granted if TTSJV can clearly establish that BapCo was precluded from making the call in this case by the terms of the parties’ contract” (at [26]). Of the earlier High Court decisions in the TCC, he followed Permasteelisa v Bouyguesstroi (2007) and MW High Tech v Biffa (2015), which had required more, read Simon Carves v Ensus (2011) as consistent with them, and declined to follow Doosan Babcock v Mabe (2013) so far as it allowed relief on a seriously arguable case of breach (at [22]–[26]).
The penalty argument: a strong presumption, and no final view
Clause 12.5 permitted BapCo to use the works prior to take-over and retain any revenue generated, but nothing adjusted the delay liquidated damages. On TTSJV’s case, the liquidated damages clause therefore protected no legitimate interest but handed BapCo an unjustified windfall, so it was penal and BapCo was limited to general damages (at [29]).
TTSJV relied on Bramall & Ogden v Sheffield City Council (1983). BapCo disputed the facts and relied on Eco World v Dobler (2021), where the failure to reduce the rate for partial completion was a factor in the balance but not fatal (at [29]–[36]). Both are first-instance decisions.
The applicable test, as Lord Hodge put it in the Supreme Court in Cavendish v Makdessi (2015), is whether the sum stipulated is “exorbitant or unconscionable when regard is had to the innocent party’s interest in the performance of the contract” (at [34]).
Drawing on Cavendish, Pepperall J considered that “the strong initial presumption must be against finding the carefully negotiated provisions for liquidated damages in this contract between commercially sophisticated parties to amount to an unenforceable penalty” (at [37]). The most TTSJV had shown was a potentially arguable case that the damages might be penal for failing to reflect the partial take-over of the facility. Nor, unlike in Bramall, had it been shown that the drafting had gone wrong so as to make the scheme unworkable (at [37]).
The answer would depend on all the factors, including party autonomy, the very real benefits of certainty, the modernisation context, BapCo’s legitimate interest in completion of the whole of the works, the apparent concession that at least US$100 million was payable, and a fact-sensitive analysis of proportionality. That could not be finally assessed on an urgent application heard at very short notice, with limited evidence served on one side only (at [37]). He held that TTSJV had not clearly established a penalty; even on its own test, it had not persuaded him of a strongly arguable case (at [38]).
The challenge to the demand failed
Clause 11 of the guarantee incorporated the Uniform Rules for Demand Guarantees (2010 revision), and TTSJV argued that the demand lacked the statement of breach required by article 15(a) (at [39]). Demands had to be substantially in the form of exhibit 1 to the guarantee, which certifies entitlement under an agreement to be named in a blank, and BapCo named the EPC contract (at [40]–[41]).
The judge rejected TTSJV’s reading of the blank as a place for details of BapCo’s claim: it was the only place in the form to identify the EPC contract (at [42]–[43.1]). In any event, article 15(a) allows the statement to be “in the demand or in a separate signed document accompanying or identifying the demand” (at [43.2]). TTSJV’s acceptance, for the purpose of the hearing, that there had been a supporting statement, not put before the court, was fatal to the argument (at [44]).
No clear case that the damages were not due and payable
TTSJV argued that, under the EPC contract and a settlement agreement, delay liquidated damages were due only so far as the delay was not excused by events entitling it to an extension of time (at [45]). It accepted that no clause postponed liquidated damages until its claim was resolved. Clause 3.5(c) requires each party to give effect to each agreement or determination despite any notice of dissatisfaction or pending arbitration. The judge, who said he should have been referred to the clause, observed without having heard argument that it “appears to dispose entirely of” this ground (at [48]–[49]).
In any event, BapCo had finally rejected the claims on 3 May 2026 in a determination enclosing a 34-page report with seven specific grounds, and there had been no attempt to engage with its detail (at [50]). Even on TTSJV’s test there was no strongly arguable case that the extension of time claim had been wrongly rejected and, certainly, no clear case that the damages were not due and payable (at [50]–[51]).
The retention bond secured liquidated damages too
TTSJV at first argued that the Mashreqbank retention bond did not secure delay liquidated damages. But paragraph 11(d) of Annex 12 allows it to be called in relation to specified circumstances in paragraph 18 (the owner’s right to set off, deduct or withhold), including “any claim to money that the Owner may have against the Contractor whether for damages (including liquidated damages) or otherwise” (at [52.1]–[52.2]). That set-off right is subject to at least three days’ prior written notice of BapCo’s intention to set off or deduct a particular amount, and to the contractor having failed to pay that amount before the proposed date (at [52.2]). The ground had no merit and was abandoned (at [53]).
Comment
Other High Court judges should generally follow this judgment but are not bound by it, and the threshold remains contested at first instance: Doosan spoke of a “strong case” (at [24.1]) and, obiter, so did HHJ Stephen Davies in CR Construction v Barclays [2026] EWHC 202 (TCC), an application against a bank that the judgment does not mention, relying on Simon Carves, which Pepperall J read as consistent with the stricter test (at [21], [26]). Nor did the choice of test decide this case: the penalty and extension of time grounds would have failed even on TTSJV’s lower test (at [38], [51]).
Three features matter for other cases: the demand followed the guarantee’s form and, it was accepted for the purpose of the hearing, came with a separate statement of breach; TTSJV relied on no express restriction on calling the performance guarantee of the kind at issue in Simon Carves (the bond to be null and void once an acceptance certificate issued) or Sirius, its penalty and extension of time grounds going instead to whether liquidated damages were owed; and the arbitration agreement offered an emergency arbitrator, confining the court to temporary relief.
This regime governs on-demand instruments such as this one. Under a default bond the surety is liable only so far as the contractor is, so check the bond’s terms, not its label (Ziggurat v HCC (2017)).
One question was not reached: whether a clearly established penalty, or proof that no liquidated damages were due, would have been enough to restrain the call.
Practical takeaways
For contractors
- Put any protection in the bond itself, such as a requirement that a demand be accompanied by an adjudicator’s decision, an award or an independent certifier’s certificate, as well as in the contract: a contractual restriction alone binds only the employer.
- If the employer may use the works and keep the revenue before take-over, agree workable machinery to reduce the liquidated damages, such as sectional rates or a revenue credit.
- If a call is threatened or made, apply at once for an emergency arbitrator where available and, if the bank may pay first, to the court under s.44, seeking relief against the employer: absent fraud, the court will not restrain the bank from paying a demand that complies with the bond (CR Construction v Barclays).
- Check what accompanied the demand, engage with any determination you challenge, and be ready to offer a fortified cross-undertaking.
For employers
- Use the guarantee’s prescribed form, with any statement of breach the incorporated rules require in the demand or a separate signed document accompanying or identifying it.
- Check the underlying contract as well as the bond: a call that the contract clearly precludes can still be restrained.
What next
No appeal or later judgment in this dispute has been reported; any appeal from a s.44 decision by a party or proposed party to the arbitral proceedings needs the leave of the court (s.44(6A)–(7)). The penalty, extension of time and liquidated damages disputes remain for arbitration.
This article is for general information only and is not legal advice.
More insights
TCC sends freeholder’s termination of a building safety remediation agreement to trial
A freeholder terminated a developer’s remediation agreement for delay two days after telling a tribunal it should keep working with it. The TCC refused summary judgment: the pressure of a remediation order does not of itself change the test for repudiation.
Read the case noteClaiming liquidated damages under the JCT Design and Build Contract 2024
The notices an employer needs to claim liquidated damages under JCT DB 2024, in order: the Non-Completion Notice, the clause 2.29 notices and the Pay Less Notice, with the clauses behind each.
Read the guideTCC: draft final account was not the Final Statement; prior correspondence was not notice
A contractor's draft final account was not its Final Statement under an amended JCT Design and Build Contract 2016. Correspondence before the Final Statement was issued could not be notice disputing it, so the employer's objections from 2022 did not count.
Read the case note